Project is divided into Tasks. In ERPNext, you can also create a Task independently.
A Task can have either of the following status - Open, Working, Pending Review, Closed, Cancelled.
By default each new Task created shall have the status set to 'Open'.
If a Time Log is made against a task, its status shall be set to 'Working'.
You can specify a list of dependent task under the 'Depends On' section.
You cannot close the parent Task until all 'Dependant Task' are closed.
If the Dependent Task are delayed and overlap with the expected Start Date of the Parent task, the system will reschedule the parent task.
ERPNext uses Time Log to track the progress of a Task. You can create multiple Time Logs against each task. The Actual Start and End Time along with the costing shall then be updated based on the Time Log.
You can book Expense Claim against a task. The system shall update the total amount from expense claims in the costing section.